The following matrix is intended to reduce internal RFP inconsistencies and aid in proposal preparation. It is provided as a reference tool for information only. In the event of conflict between this matrix and any other section of the RFP, the other section shall take precedence.
WORK DESCR |
WBS ELEM |
SOW PARA |
CLIN |
CDRL |
INSTR TO OFFERORS (SEC L) |
EVAL FACTORS (SEC M) |
PROP LOC |
Design B |
2.2 |
3.2.2 |
0001 |
N/A |
3.B.1 |
Tech 1.A |
V1-p.64 |
Build A |
2.3 |
3.2.3 |
0002 |
A001 |
3.B.2 |
Tech 1.B |
V1-p.75 |
FIGURE 2. Cross reference matrix.
3.6 Standard Format. The standard format for the SOW is as follows (subject to variations specified in Section 4 for specific types of SOWs):
SOW Section Title
1 SCOPE
2 APPLICABLE DOCUMENTS
3 REQUIREMENTS
Deviations from the standard format may be made by the writer when necessary to accommodate overriding program needs.
3.6.1 SOW Section 1 - Scope. This Section includes a brief statement of what the SOW should cover. The scope paragraph defines the breadth and limitations of the work to be done. In some cases, the use of an introduction, background, or both, is preferred. Separate indentures under this Section are used in SOWs to accommodate complex acquisitions requiring lengthy background information. Background information should be limited to only that information needed to acquaint the proposer with the basic acquisition requirement. The items listed below should not be included in the "Scope" Section.
a. Directions to the contractor to perform work tasks. b. Specification of data requirements.
c. Description of deliverable products.